(edit on Mar 28) During February, there are few things that were done, and will be done in March
Finished Tasks
1. IHM Blade has halted and needs replacement, following steps are performed:
(a) Replace System board
(b) Reconfigure VIOS
(c) Restart QCONSOLE and make it work
(d) Make AS400 work
2. Saint Rosa X3650 M4 fixed with system board replaced
3. Some HDD are replaced
4. DSF HMC fixed!!! Operator console replaced for BCM
Ongoing tasks (Edited on March 19th)
1. IHM relocation (Done)
2. Venetian Power 8 Installation (Some completed on March 26th)
This one got postponed to April 1st/2nd due to tape drive cannot backup Critical applications data
3. HMC upgrades for QA and DEV (Not sure)
New tasks:
DSF Upgrade OS for V7R3
LPAR UAT: Done on March 14-15th
LPAR DEV: Done on March 20-21st
LPAR Backup: Scheduled on April 3-4th
LPAR Production: Scheduled on April 19th-21st